Border Crossings: Bulgaria - North Macedonia: Difference between revisions

From EGTRE
Jump to navigationJump to search
m (EU support for Kumanovo - Deve Bair)
Line 1: Line 1:
Note that there is a one hour time difference between Bulgaria and North Macedonia.  
Note that there is a one hour time difference between Bulgaria and North Macedonia.  


==(Skopje - Kumanovo -) Beljakovce MŽ - Gjueshevo BDŽ (- Sofia)==
==(Skopje - Kumanovo -) Deve Bair MŽ - Gjueshevo BDŽ (- Sofia)==
This route has been planned for many years. Construction of the Kumanovo - Beljakovce section began in March 2014. Completion was allegedly planned within two years but it has been postponed several times. On 29 May 2020 the contractors terminated the contract, with the work only half complete. On 14 July 2017 the European Union announced it would finance construction of the whole line on the understanding that it would be completed by 2025/2027 but then in October 2021, Ministers from Bulgaria, Albania and North Macedonia signed a memorandum to complete by 2030, but only with significant investment and not explaining its source...  
This route has been planned for many years and part of the line from Kumanovo as far as Beljakovce was completed as long ago as 1956.  Having previously been identified as part of Pan-European Corridor VIII it was also adopted as part of the EU Western Balkans expansion as a strategic east-west corridor and funding assistance was arranged. Rehabilitation of the Kumanovo - Beljakovce section began in March 2014 with completion targeted within two years, but it was delayed several times and on 29 May 2020 the contractors terminated the contract with the work only around half complete.
 
The EU’s Economic and Investment Plan for the Western Balkans published in October 2020 identified this route as one of their flagship investment priorities.  In October 2021, Ministers from Bulgaria, Albania and North Macedonia signed an agreement to complete the entire Corridor VIII route through their countries by 2030.  By the start of 2022 the EU had made €283m available in loans and grants for the Kumanovo – Deve Bair line.


No work has yet been undertaken on the Bulgarian side of the border.
No work has yet been undertaken on the Bulgarian side of the border.

Revision as of 14:42, 3 February 2022

Note that there is a one hour time difference between Bulgaria and North Macedonia.

(Skopje - Kumanovo -) Deve Bair MŽ - Gjueshevo BDŽ (- Sofia)

This route has been planned for many years and part of the line from Kumanovo as far as Beljakovce was completed as long ago as 1956. Having previously been identified as part of Pan-European Corridor VIII it was also adopted as part of the EU Western Balkans expansion as a strategic east-west corridor and funding assistance was arranged. Rehabilitation of the Kumanovo - Beljakovce section began in March 2014 with completion targeted within two years, but it was delayed several times and on 29 May 2020 the contractors terminated the contract with the work only around half complete.

The EU’s Economic and Investment Plan for the Western Balkans published in October 2020 identified this route as one of their flagship investment priorities. In October 2021, Ministers from Bulgaria, Albania and North Macedonia signed an agreement to complete the entire Corridor VIII route through their countries by 2030. By the start of 2022 the EU had made €283m available in loans and grants for the Kumanovo – Deve Bair line.

No work has yet been undertaken on the Bulgarian side of the border.

See also